Building a Deltec Home

In many cases a Deltec home can be in the dry in about a week, depending on your crew and site conditions.

Page 1     Page 2

DAY 3* Roof erection jig set in place

DAY 3* Begin setting roof trusses

DAY 3* Intermediate and hip trusses set

DAY 3* Jack trusses set

DAY 3* Tension collars installed

DAY 4-5* Roof sheathing applied

DAY 5* House dried in, interior framing begins

DAY 5+ Decks, trim installed, siding stained/painted

DAY 5+ Finished roofing applied. Rainbow not included

 